April 24, 2017 Weekly Update

Work began this week on relocating the existing chiller lines at the Radisson Paper Valley Hotel.

Testing of tieback anchors continued, as well as pipe pile installation. Excavation crews worked with the pipe piling and concrete crews to remove soils for grade beams and pile caps. The northeast corner of the building was formed and rebar was installed in preparation for a concrete pour on Saturday. It rained periodically throughout the week; the schedule was maintained, however crews had to rearrange concrete pours each day to work around the weather.