Excavation of the various pile caps continued this week. Final grouting of the tiebacks occurred and the testing is nearly complete for all of the tieback anchors.
The pipe piling crew worked tirelessly to ensure they stayed ahead of the concrete and rebar crews, and they were able to install more than forecasted. Rebar crews began tying the rebar that was already onsite; the freight elevator pit and northeast elevator pits were completely tied in preparation for concrete crews to pour in the coming week. Site conditions were very muddy, however no work was delayed.