August 14, 2017 Weekly Update

Escalators have been set at the Radisson Paper Valley Hotel.

Miscellaneous steel angle is being placed in preparation for precast panels at plaza level. Masons continue work in the exhibition hall, and have started placing natural stone on the exterior of the northeast elevator shaft on West Lawrence Street. Site conditions are good, and there were no injuries this week.