The construction crew completed excavation of the Tier 2 soils, with the exception of a small portion that had to remain in place for re-grouting of tieback anchors.
Work on Tier 2 tieback anchors progressed on the north and south ends of the project site; once this is completed, crews will begin on the Tier 3 level. Due to snowy conditions on Thursday evening, crews spent Friday ensuring the site and surrounding areas were cleared of snow and ice.