Backfilling of foundations for the walkway bridge at the Radisson Paper Valley Hotel is complete, and the area is ready for structural steel and precast panel installation.
Slab on grade concrete has been poured for the west portion of back-of-house, the service corridor, and the lower level stair slab in the southwest corner of the exhibition center level. Masons completed the freight elevator walls and are working on the loading dock walls.