Foundation work continues for the elevator and escalator at the Radisson Paper Valley Hotel.
Steel erection for the plaza level/exhibition hall roof occurred this past week; two plate girders were set and steel decking is being installed for deck pours this week. Concrete pours continue along the southeast corner of the project site, and the masonry crew is building walls in the southwest corner for the loading dock/service area. There were no issues or injuries this week.