Mass excavation was fully completed this week, and all tieback anchors have been installed. Work continued on removing the existing buried foundations, as well as excavating soils in preparation for pipe pile installation.
The Miron crew poured a mud slab in the center of the building footprint to serve the entire perimeter receiving concrete. Forms and rebar were staged on the slab for the coming week when concrete will start following the pipe pile installation. The weather was fairly mild this week, and crews were able to maintain a great production rate.