On-site crews constructed temporary walls inside the Radisson Paper Valley Hotel in order to contain construction areas and demolition work.
New chiller lines were installed and prepped to be connected to the system. Excavation crews continued to dig for grade beams and pile caps. Work also continued on the north wall, with crews pouring approximately halfway down the wall. Masonry began this week with the northeast elevator shaft. No injuries occurred this week.