MEP work at the Radisson Paper Valley Hotel as well as roadwork on Lawrence Street continues.
There is quite a bit of steel work being done, including installation of handrails, ladders, and stairs. The entire exhibition floor has been poured. Work on the masonry column wrap continues, along with interior stone veneer around the elevator shaft walls.