Exterior framing continues, spray foam under the crosswalk started this week, and precast work is complete at the Radisson Paper Valley Hotel.
Stairs spanning from the plaza to bridge level are being reinforced, and installation of steel continues including handrails, ladders, stairs, etc. The south third of the exhibition hall floor has been poured and finished. Installation of interior stone veneer around the elevator shaft walls continues, and masonry around the expo columns has begun.