Work continues at the Radisson Paper Valley Hotel with roof blocking, exterior framing, and precast.
Bridge steel is complete and metal decking has been installed. The crosswalk slab will be poured next week. Slab on grade preparation continues with the installation of floor boxes and site grading. Exterior stone veneer around the elevator shaft walls is complete, and interior stone will be finished in the coming weeks. Work is also being done on the interior CMU walls of the exhibition hall and pre-function areas.